Understanding Application Numbers
Each AIA style billing application is assigned a sequential application number (e.g., 1, 2, 3). This number tracks the billing period and ensures proper progression of billing.
Creating a New Billing Application
Follow these steps to create a new AIA billing application:
- Open the AIA Billing Tool.
- Open the job with AIA style billing enabled.
- Click the AIA Style Billing button in the side toolbar.
- The system will automatically determine the next application number.
Initially, this will be empty.

As users create jobs with AIA billing enabled, they will appear in the list.

- Enter Application Information.
- Select the application in the list and click Open or click New.
- Application Number: Auto populated with the next sequential number.
- Application Date: The date of this billing application (defaults to current date).
- Period To: The billing period covered by this application.

- Review Scheduled Values.
- The Continuation Sheet form (Scheduled Values tab) will automatically populate with your install items.
- Each line shows these:
- Column A: Item number
- Column B: Description of work
- Column C: Scheduled value (from install items)
- Column D: Previous applications (auto calculated from prior applications)
- Column E: Work completed this period
- Column F: Materials presently stored (if applicable)
- Column G: Total completed and stored to date (auto calculated)
- Column H: Retainage (auto calculated based on percentage)
- Column I: Total earned less retainage (auto calculated)

- Enter Current Period Values.
- For each line item, enter the value in Column E (work completed this period).
- If applicable, enter values for Column F (stored materials).
- The system will automatically calculate totals and retainage.
- Save the Application.
- Click Save to save your work in progress.
- You can return to edit the application before finalizing.